No-work weeks and final payroll

When no work is performed in a week and when to file the final certified payroll.

No-work weeks

When a contract is active but no covered work is performed in a given week, most agencies require a no-work report. This is a certified payroll form that states no work was performed on the project that week.

The no-work report:

  • Gets the next payroll number in sequence (do not skip numbers).
  • Shows the week-ending date.
  • States that no work was performed.
  • Is signed the same way as a regular payroll (the Statement of Compliance still applies to the statement that no work was done).

Some agencies accept a letter or memo instead of a blank WH-347. Others require the full form with zero workers. Check the agency's instructions and your contract.

When to submit no-work reports

  • Weeks between the start of work and the final payroll where no covered work was done on the project.
  • Weather delays, shutdowns, holidays, and breaks in work while the contract is still active.
  • Periods when only non-covered work (not subject to Davis-Bacon) is performed. Workers doing non-covered work do not appear on the certified payroll, so the week may be a no-work week for certified payroll purposes.

You generally do not need to submit no-work reports for weeks before the first week of work or after the final payroll.

Final payroll

The final certified payroll is the last payroll for the contract. On the January 2025 WH-347, tick the "Submission of final DBRA certified payroll" checkbox at the top of page 1.

The final payroll includes the last week of work (which may be a partial week) and covers any remaining workers on the project. After the final payroll, no more certified payrolls are due for that contract.

If a no-work week falls between the last week of work and the submission of the final payroll, include that no-work week as a separate report before the final payroll.

Payroll numbering

Number each certified payroll in sequence, starting at 1 for the first payroll on the contract:

  • Payroll no. 1: first week of work.
  • Payroll no. 2: second week (or no-work report if no work that week).
  • Continue in order. Do not skip numbers for no-work weeks.
  • The final payroll gets the next number in sequence.

If you need to amend a payroll, the amendment is typically submitted as a correction to the original payroll number, not as a new number. Check the agency's amendment procedures.

FAQ

Do I have to submit certified payroll for weeks with no work?

Most agencies require a no-work report for any week the contract is active but no covered work was performed on the project. The report states that no work was done that week. Check your contract and the agency's requirements.

What is the final payroll?

The final certified payroll is the last payroll submitted for a contract. On the January 2025 WH-347, you tick the "Submission of final DBRA certified payroll" checkbox at the top of page 1. This tells the agency that no more payrolls will follow for this contract.

Certified Payroll App handles no-work weeks in one click and marks the final payroll with the checkbox. Get started (Starter $79/month).

Updated November 2026. Source: 29 CFR 5.5(a)(3)(ii), Form WH-347 (Rev. January 2025) instructions, DOL Wage and Hour Division guidance. This is general information, not legal or payroll advice. Check your contract and the agency's instructions.

Pricing Contact Terms Privacy GuidesAbout Sign in

Certified Payroll App is independent software. It is not affiliated with or endorsed by the U.S. Department of Labor, SAM.gov, the California Department of Industrial Relations, LCPtracker, Gusto, Intuit QuickBooks, ADP, Paychex or Viewpoint. You review and sign your own certified payrolls. Certified Payroll App is operated by Owusu LLC.